BC Hydro Site C commissioning support on a 1,100 MW development

Long-term embedding in the AtkinsRéalis / BC Hydro commissioning team.

BC Hydro's Site C project, on the Peace River, totals about 1,100 MW. Since 2023, on 14-days-on / 7-days-off camp rotations, FORWA supports AtkinsRéalis over more than 7,000 hours centered on the unit control board (UCB): commissioning planning, dry walk-down with Voith, cable completion verification, daily work reports and punch-list follow-up.

Highlights

  • UCB commissioning coordination
  • Dry commissioning walk-down with Voith
  • DWR and punch-list follow-up

Results

  • Long-term commitment on a national scale project
  • Embedded with major owner/contractor teams